Project Schedule
Schedule as of November 13, 2007
The City Council on January 22, 2007 approved a contract with WSB & Associates, Inc. to assist in the development and prepare the necessary construction documents for Woodley Street (CSAH 28).
The City will be hosting their third neighborhood meeting on November 13, 2007 from 5:30 p.m. to 7:00 p.m. at City Hall. At this meeting, striping, tree replacement, burying of overhead utilities, and the project schedule along Woodley Street from Prairie Street to Jefferson Parkway will be discussed.
The following is a brief schedule outline:
Project Development Phase |
|
|---|---|
| First Neighborhood Meeting | March 8, 2007 |
| Preliminary Concept Development | March 12 to September 10, 2007 |
| Second Neighborhood Meeting | June 20, 2007 |
| Present Feasibility Report to City Council | July 16, 2007 |
| Present Layout to City Council | July 16, 2007 |
| Right-of-Way Limits Set | September 10, 2007 |
| Start Right-of-Way Appraisals | September 17, 2007 |
| City Council Accepted Feasibility Report | October 1, 2007 |
| City Council Approved Layout | October 1, 2007 |
| Written Offers | Mid-November 2007 |
| Third Neighborhood Meeting | November 13, 2007 |
| City Council Plan Approval | December 2007 |
| Right-of-Way Negotiations | December 2007 to February 2008 |
| Right-of-Way Aquired | March 2008 |
| Mn/DOT Plan Approval | April 2008 |
| Open Bids | Late July 2008 |
| Award Contract | Early August 2008 |
Construction Phase |
|
|---|---|
| Neighborhood Meeting | Late June 2008 |
| Begin Construction | Early July 2008 |
| Phase I: Jefferson Parkway to Farehaven Court | November 20, 2008 |
| Phase II & III Construciton | Late July 2009 |
| Final Wearing Course | Mid-July 2009 |