Project Schedule

Schedule as of November 13, 2007

The City Council on January 22, 2007 approved a contract with WSB & Associates, Inc. to assist in the development and prepare the necessary construction documents for Woodley Street (CSAH 28).

The City will be hosting their third neighborhood meeting on November 13, 2007 from 5:30 p.m. to 7:00 p.m. at City Hall. At this meeting, striping, tree replacement, burying of overhead utilities, and the project schedule along Woodley Street from Prairie Street to Jefferson Parkway will be discussed.

The following is a brief schedule outline:

Project Development Phase
First Neighborhood Meeting March 8, 2007
Preliminary Concept Development March 12 to
September 10, 2007
Second Neighborhood Meeting June 20, 2007
Present Feasibility Report to City Council July 16, 2007
Present Layout to City Council July 16, 2007
Right-of-Way Limits Set September 10, 2007
Start Right-of-Way Appraisals September 17, 2007
City Council Accepted Feasibility Report October 1, 2007
City Council Approved Layout October 1, 2007
Written Offers Mid-November 2007
Third Neighborhood Meeting November 13, 2007
City Council Plan Approval December 2007
Right-of-Way Negotiations December 2007 to February 2008
Right-of-Way Aquired March 2008
Mn/DOT Plan Approval April 2008
Open Bids Late July 2008
Award Contract Early August 2008

Construction Phase
Neighborhood Meeting Late June 2008
Begin Construction Early July 2008
Phase I: Jefferson Parkway to Farehaven Court November 20, 2008
Phase II & III Construciton Late July 2009
Final Wearing Course Mid-July 2009